This paper presents a site-survey method for measuring construction waste at building sites and expressing it as category-wise percentages. Waste is sorted at source into ten categories (concrete and mortar, bricks and blocks, tiles, steel, timber, plastics and packaging, plaster and gypsum, glass and aluminium, paint and chemicals, soil and other), weighed on site across three construction stages, and analysed for percentage share, waste generation rate per m² of built-up area and material wastage percentage. Published studies show compositions ranging from masonry-dominated to timber-dominated depending on construction system, and Indian national estimates of C&D waste vary by more than an order of magnitude, which shows the need for site-level data. A worked example with placeholder figures illustrates the analysis, and the paper closes with minimization measures arranged by the waste hierarchy. Field data should replace the placeholder values in Section 4 before the findings are reported.
Introduction
The study focuses on Construction and Demolition (C&D) Waste Generation Assessment at Building Sites, aiming to identify, measure, and analyse different types of construction waste and suggest effective methods for reducing it.
Construction waste is a major environmental concern in rapidly developing countries like India. A large quantity of waste is generated during building construction, including concrete, cement mortar, bricks, steel, timber, tiles, plastics, and packaging materials. However, only a small proportion of this waste is properly recovered and recycled. Most existing estimates are based on national-level data, while site-level measurements are limited.
The main aim of the study is to assess construction waste generation through field surveys at building sites. Its objectives are to identify and categorize waste materials, measure their quantities by weight, calculate their percentage contribution to total waste, estimate waste generation per square metre of built-up area, identify the major causes of waste, and recommend suitable waste-minimization measures.
The literature review highlights that construction waste composition varies according to building type, construction methods, and project stages. Common causes of waste include improper storage and handling, material breakage, over-ordering, poor site supervision, inefficient cutting, excessive mixing, and rework due to construction errors.
The proposed methodology involves conducting a site survey at different types of residential, commercial, and institutional buildings. Waste materials are divided into ten categories: concrete and cement mortar, bricks and blocks, tiles and ceramics, steel, timber, plastics and packaging, plaster and gypsum, glass and aluminium, paint and chemicals, and excavated soil and mixed waste.
Data collection involves sorting and weighing waste materials, examining purchase and consumption records, observing site practices, taking photographs, and interviewing site engineers and supervisors. Mathematical calculations are used to determine the percentage composition of each waste category, waste generation rate in kg/m², and material wastage percentage.
The illustrative results show that bricks and blocks contribute 26% of total waste, while concrete and cement mortar contribute 23%. Together, these materials account for 49% of the total waste. The example also groups waste according to management methods:
Inert and crushable waste (74%): Concrete, bricks, tiles, and soil, which can be reused as filling materials or recycled aggregates where suitable.
Recyclable waste (17%): Steel, timber, plastics, and glass, which can be reused or sent for recycling.
Residual and hazardous waste (9%): Plaster, gypsum, paint, and chemicals, which require appropriate handling and disposal.
The illustrative waste generation rate is 41.7 kg/m², based on 12,500 kg of waste and 300 m² of completed construction. These figures are hypothetical examples and must be replaced with actual field survey measurements before drawing final conclusions.
The discussion emphasizes the importance of identifying major waste-generating activities at different construction stages. For example, excavation produces soil waste, masonry generates broken bricks and mortar, and finishing work produces tile off-cuts, packaging, and leftover materials. Proper storage, careful material handling, accurate estimation, reuse of materials, waste segregation, and better site supervision can significantly reduce construction waste.
Conclusion
The study sets out a repeatable site-survey protocol that sorts building-site waste into ten categories, weighs each category, and reports its percentage share, a generation rate per m² and material wastage percentages. In block-and-RCC building the expected pattern, to be confirmed with the survey data, is that masonry, concrete and mortar form the largest share by weight, so on-site handling, storage and mixing practice are the first places to act. Waste grouped by management route shows how much can be crushed for reuse, sold or must be disposed of separately.
Limitations to state in the final paper:
• The sample of 8 to 12 sites cannot represent all building types or regions.
• A one-week sampling window per stage may miss irregular large wastes such as formwork stripping.
• Weighing by hand sorting has measurement error, and volume-to-weight conversion adds uncertainty.
• Results exclude demolition and renovation waste and off-site losses.
Future work could add cost valuation of waste, comparison of sites with and without a waste management plan, and tracking of waste after it leaves the site.
References
[1] Centre for Science and Environment (2020). India manages to recover and recycle only about 1 per cent of its construction and demolition waste.
[2] Central Pollution Control Board (2017). Guidelines on Environmental Management of C&D Waste in India (draft).
[3] Ram, V. G. and Kalidindi, S. N. (2017). Estimation of construction and demolition waste using waste generation rates in Chennai, India. Waste Management & Research.
[4] Jain, S., Singhal, S. and Jain, N. K. (2019). Construction and demolition waste generation in cities in India: an integrated approach. International Journal of Sustainable Engineering.
[5] Waste Management World. Rebuilding C&D waste recycling efforts in India.
[6] Kechika, P. (2022). An analysis of material waste generated on construction sites within Kampala. Undergraduate dissertation, Makerere University.
[7] University of Peradeniya. Construction and demolition waste generation and its management in Sri Lankan building construction projects.
[8] Construction and demolition waste dynamics in the building construction sector in Sri Lanka. Engineer.
[9] Categorization and quantification of construction waste of commercial buildings in Iraq. See also E3S Web of Conferences, 2023.
[10] Waste composition in Yazd, Iran (2017 to 2018 sampling).
[11] Composition of construction waste, Malaysia.
[12] Material wastage factors in Indian practice. InfraLens (secondary source).
[13] Factors affecting cement and steel reinforcement wastage. EIJEST.
[14] Ministry of Environment, Forest and Climate Change. Construction and Demolition Waste Management Rules, 2016 (summary) and published rules text including the 2025 supersession.
[15] GPSC (2017). Presentation on a C&D waste case site.