Authors: Himanshu Maurya, Dr. Gaurav Shukla
DOI Link: https://doi.org/10.22214/ijraset.2024.60855
Certificate: View Certificate
Project management is the practice of organizing, planning, carrying out, overseeing, and wrapping up a team\'s work in order to accomplish particular objectives and satisfy particular success criteria within a given time frame. Each project is unique, and managing it is necessary to meet the project\'s need for increased productivity. Notwithstanding the centuries-long evolution of the construction industry and the decades-long quest for novel solutions by researchers, a variety of obstacles still need to be overcome in order to improve the speed, safety, affordability, and accuracy of the construction process. Utilizing a program called Prima Vera p6, which is a tool for project planning and progress tracking, the study focuses on an ongoing residential building construction project (G+5) . This project is a G+5 storey residential building with a rectangular shape RCC framed construction with a total size of 1391 Sq. Mtr. And the floor height is 3m. We used Primavera to calculate project quantities, schedule, and estimate the project. We created a Gantt chart and a network diagram for this project and completed it in a timely and cost-effective manner. It gathers all relevant data from the relevant agencies and closely monitors the work processes. Through our work on it, we have learned a great deal about the challenges that businesses encounter on a daily basis. Though every project is unique, as I\'ve already shown, we may learn from our mistakes and prevent them in future endeavors. Using Primavera P6, a project management tool, a comparison of the original and actual time and cost is conducted in this study. The project monitoring process itself might not be completed effectively even with well-established planning and policies.
I. INTRODUCTION
Cost overruns and delays in building projects have long been an issue in the construction and engineering industries. Increases in both time and expense in big public construction projects. Optimistic schedule and budget expectations have been proven to reduce the degree of quality and productivity during the building stage and in the final end-product. To reduce such overruns, the existing corpus of knowledge tends to focus on crucial success elements such as time and cost as discrete notions of different project kinds and geographical locations with minimal context. A successful project is defined as the capacity to satisfy both the contract's budget and timeline. However, in addition to earlier research, we must incorporate quality into the argument of time and cost as connected notions, since all three have been prominent in the building literature, sometimes known as the "iron triangle." Comprehensive research concentrating on time, cost, and quality as interconnected concepts are thus required to establish major disparities between the three ideas in the "iron triangle" and to expand the current body of knowledge.
Increased pre-project planning work might be a viable answer to the essential success factors influence on building projects. The advantages of employing pre-project planning include higher profit, less risk, and improved quality.
In comparison to a reactive approach, increased construction planning allows the contractor to be more proactive in responding to crucial elements affecting the project. The benefits of realistic cost and time planning prior to design, as well as its effectiveness throughout the construction stage, include enhanced project outcomes, user satisfaction, and lower project cost and duration. Identifying and testing for substantial variances in the impacts of the essential success variables on time, cost, and quality is thus critical to deal with the issues in the pre-project planning phase to ensure the project outcome.
On-time completion of projects is an evidence of an efficient construction sector. In reality, a project is deemed ‘successful' if it is finished on schedule, within budget, and to the required quality. When projects are delayed, they are often either prolonged or expedited, incurring more costs. Many projects, much to the chagrin of owners, contractors, and consultants, incur lengthy delays and thereby surpass initial time and expense projections. The building process is fraught with uncertainty and unpredictability. Delivering a project on time does not happen by hoping that the deadline will be reached.
To design and execute a successful project, three aspects must be considered: time, money, and quality. Construction clients are generally concerned about quality, timeliness, and cost. However, the bulk of construction projects are bought based on schedule and cost limitations. Poor management techniques are commonly related with cost escalation and time overruns.
As a result, effective project management is dependent on the management tools. Managing resources includes overseeing personnel, equipment, finances, supplies, and techniques. While some projects are successfully and economically managed, others are poorly managed, resulting in significant delays and cost overruns that have a detrimental impact on the economy.
II. OBJECTIVES OF STUDY
III. METHODOLOGY
Following a review of the literature to determine how IT is used in civil engineering and to develop goals that take software's PRIMAVERA into account, the following approach has been thoughtfully created to meet these goals.
A. Steps Involved In Monitoring And Controls Of Project Are
Establishing the perfect timetable Any project's initial step in creating a schedule is gathering all of the project's data. Primavera can then be used to carry out the succeeding phases.
7. Determining Activity Duration: When planning the work, the duration is entered in the original duration field. The actual duration can only be entered for the activities, which are completed.
8. Activity Dates: The following are the types of activity dates available in the primavera actual start, actual finish, planned start, and planned finish.
9. Activity Cost: The activity cost is the sum of all the cost incurred to complete the activity. It may be consist of Labor cost + Material cost = Total Cost.
10. Creating Baselines: A simple baseline plan is a complete copy of the original schedule which provides a target against which a project’s performance is tracked.
11. Updating schedule
12. Tracking: Tracking window is used to monitoring a process of a project using different types of layouts such as labor costs, project cost, resource forecasting, resource allocation unit wise and cost wise.
13. Earned Value: Earned value is a technique for measuring project performance according to both project cost and schedule. The technique compares the budgeted cost of the work to the actual cost.
14. Project Issues: Project issues are the problems which a site engineer or a site in charge faces while executing the work of the project. Problems can be resolved by paying attention on time and finding the solution to it.
IV. FACTORS THAT AFFECT COST AND TIME IN CONSTRUCTION PROJECT
A. Delays
As observed from the analysis above, one of the most common effects of cost overruns was delay. Delays in project completion can be attributed to factors such as:
B. Additional Costs
First Added Works Throughout the building phase, additional activities are required as a result of design changes. A specific project must be completed, so the extra expense will be necessary. Additional funding and labor are needed for this, and planned adjustments must be made in between the project phases.
2. Fluctuations Indian Construction Projects
High rates of inflation lead to increases in labor and service expenses, as well as material prices. This causes fluctuations. For the duration of its phase, fluctuations are highly typical. The introduction of new levies, such as the GST, also causes fluctuation. Since India is not a developed nation like the US dollar, British pound, etc., material prices will fluctuate greatly to reflect changes in the currency rate. It is expected that tenders quoted in India would experience volatility.
3. Inaccurate Estimates / Provisional Sums
For the client, inaccurate project cost estimation might have serious consequences. When sufficient investigations are not carried out and all work items are not accurately priced in the Bills of Quantities (BOQ) prior to the start of construction, the true costs of these work items are discovered during the building process. These expenses, which are typically added to the tender price and result in significant cost overruns, are typically greater than the tentative estimates permitted in the BOQ.
4. Adversarial Relationship among Parties
Relationship problems between the Contract's parties may arise from cost overruns. Cost overruns may cause a sharp decline in construction activity, damage to one's reputation, and make it more difficult to obtain project financing in the future. Not to be overlooked are further consequences of cost overruns:
a. The quality of the workmanship is low.
b. A contractor impacted by the client's inadequate financial flow.
c. Fair and equal distribution of resources.
d. The contract for this study is an item rate contract; the contractor is awarded the contract based on item rates and quantities, with the architectural team identifying the amounts of various products.
e. They have used the layman's method to create a timeline in Microsoft Excel for the project's completion.
f. I chose to utilize Primavera P 6 for this project after choosing this topic for my study because I wanted to find out how the current approach and the layperson technique would reduce project costs and time.
g. This software also shows us where we started with our project, how far we have come, and how much time and money we still have to go.
h. If we are falling behind in the previous action, we should attempt to shorten the actual duration of the following activity. This will save both our time and money, as time is closely correlated with money.
i. Since this is an item rate contract, the contractor must ensure that he will reduce his indirect costs by increasing his time savings.
j. The primary goal of any contractor is to complete their work within the allotted time frame, as this results in a satisfied clientele who will refer you to their friends and family.
V. RESULT AND DISCUSSION
This section examines the primary causes of cost and schedule overruns, which can stem from a variety of sources and are dependent on the project that was selected. The project under investigation is behind schedule due to inadequate planning and financial constraints.
The results were gathered based on the questions posed to the site engineers, subcontractors, and project managers. It is crucial to confirm that the site workers and the architecture company were aware of the research definitions when they provided the data for this example. The responses from the conversation provided by the site engineers, project managers, subcontractors, and client representatives are examined.
Some information about the business was provided by the respondents, and online research was used to confirm the information. Ongoing construction is tracked in a single project management software file, which is updated daily and cross-checked against the timetable that was previously established. Four interviewees admitted to holding somewhat structured meetings. Accordingly, the entire research design of this thesis centered on the four meetings that the organization's two task administrators reported, as well as the members' post-event review. We discussed two distinct activities—one with excellent execution and the other with subpar performance—with each of the undertaking administrators.
Based on the present case study the following results are determined. The various factors are tabulated as follows. Which indicates the data representation to achieve the following result,
Activities |
Actual Cost |
Predicted Cost |
Difference |
Foundation |
15,00,000 |
20,00,000 |
5,00,000 |
Ground floor |
12,00,000 |
15,00,000 |
3,00,000 |
First floor |
12,00,000 |
15,00,000 |
3,00,000 |
Second floor |
12,00,000 |
15,00,000 |
3,00,000 |
Third floor |
12,00,000 |
15,00,000 |
3,00,000 |
Fourth floor |
12,00,000 |
15,00,000 |
3,00,000 |
Fifth floor |
12,00,000 |
15,00,000 |
3,00,000 |
Roof |
7,00,000 |
8,00,000 |
1,00,000 |
Finishing |
42,56,130 |
50,00,000 |
7,43,870 |
Total amount |
1,25,76,365 |
1,68,00,000 |
31,43,870 |
The contractor had supplied us with the information that the actual duration of the project is 365 days and the total cost of the project was summed up to Rs.2 crs (approx.).
But the same project when efficiently planned using primavera software could be completed in only 265days as shown in planned schedule with the total project cost assuming up to Rs.1 crs (approx) as obtained from estimation of cost.
Therefore, it is concluded that a project could be completed 79 days earlier and would save Rs.31, 43,870.
Hence our objective of our project which were to complete the project in stipulated of time minimum resources and to maximize the resource material and equipment have been achieved.
1) We need to make sure the project is finished on schedule in order to save costs. 2) Adequate planning is essential for timely project completion. 3) To secure the greatest number of projects available in the market, contractors must guarantee a record of timely completion. 4) By using a basic planning tool, the contractor for a project could be completed 79 days earlier and would save Rs.31, 43,870. 5) Our objective of our project which were to complete the project in stipulated of time minimum resources and to maximize the resource material and equipment have been achieved. 6) The contractor is responsible for guaranteeing that the teams required to finish a specific task will be accessible on schedule. 7) Never select a subcontractor whose bid is excessively expensive or too low in relation to the total cost of completion.
[1] Kenny, C. (2010), Publishing Construction Contracts and Outcome Details, The World Bank, Sustainable Development [2] Cox, Robert F., (2007) \" Key Elements to Successful International Collaboration in Construction Project Delivery\", The proceedings of The International Conference of Construction and Real Estate Management, Beijing, China, ISBN 978-7-89475-107-2. [3] Garry D. Creedy, Risk factors leading to cost overrun in the delivery of highway construction project. Proceeding of Queensland University of technology research week international conference, 4-8 July, Brisbane, Australia. [4] Le-HoaiL,LeeYD,LeeJY. 2008. Delay and cost overruns in Vietnam large construction projects: a comparison with other selected countries. KSCE J Civil Eng. 12(6): 367–377. [5] Maceda C. 2016. 70% of Dubai projects facing delays-ana lyst. Gulf News Property. [accessed 2017 Jan 15]. http:// gulfnews.com/business/property/70-of-dubai-projects-fac ing-delays-analyst-1.1669124. [6] Memon AH, Rahman IA, Azis AAA. 2011.Preliminarystudy on causative factors leading to construction cost overrun. Int J Sustain Construct Eng Technol. 2(1): 57–71. [7] Subramani. T and Chinnadurai. K (2015), Construction Management and Schdeduling of Residential Building using Primavera International Journal of Application or Innovation in Engineering & Management (IJAIEM),4(5),188 198. [8] Prabhat Kumar Sinha, Abu Salah Mohammed Alakhdar Abdul Aziz, R.k. Pandey, Ashok Tripathi & Anshuman (2013), Time and Schedule management using Primavera, International journal of civil engineering and technology, 4(5), 78-89. [9] Chew Y.L. and Michael, 2001 Construction Technology for Tall Building. 2nd Edition, University Press and World Scientific Publishing Co. Pvt. Ltd., Singapore. [10] Mantri S., the A to Z of “Practical Building Construction and its Management”. 9. Ranjbaran A., February 2007,”Planning and Control of High-Rise Building Construction
Copyright © 2024 Himanshu Maurya, Dr. Gaurav Shukla. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Paper Id : IJRASET60855
Publish Date : 2024-04-23
ISSN : 2321-9653
Publisher Name : IJRASET
DOI Link : Click Here