Authors: Patel Kiran Kumar, Nimita Gujar
DOI Link: https://doi.org/10.22214/ijraset.2022.45750
Certificate: View Certificate
Construction duration and the cost of project at the closing date are the two important criteria to describe a construction project as successful. Most civil engineering large projects, regularly, have delays and cost overruns. Also most of the construction projects are facing with low quality, and health and safety accidents during construction. A questionnaire was undertaken to investigate factor affecting cost overrun for construction. In this project the result of the questionnaire was summarized and discussed. Major factors affecting the success of a construction project categories in the questionnaire and they were ranked with respect to the frequency and importance indices separately. It was obtained that, inadequate contractor experience, poor supervision and site management, shortage of skilled labor, financial difficulties of contractor were the most important causes of delay, cost overrun, low quality, and health & safety problems on the construction sites.
I. INTRODUCTION
The Indian construction industry contributes more than five percent (5%) to the country’s GDP. Construction industry includes railways, highways, ports, bridges, tunnels, power plants, municipal facilities etc. Timely completion of construction projects is a display of efficient planning, management and construction. A project is measured to be successful if it is complete on time and within budget.
Bridges construction industry is considered as one of the most dynamic and risky industrial sector. Also, an important key parameter to make a project successful is considered to be the budget required for the project. Many authors have suggested that risk cost should be adopted as an evaluation scale. In unkindness of the importance of this factor, construction industry is full of projects that functionally operate with extensive cost flooded. Considerable financial loss to project participant is generated by cost overflow in construction project.
II. OBJECTIVES
III. DATA COLLECTION
A. Research Methodology
The research methodology contains two stages. The primary stage included a literature search and interviews. The literature review was conducted through internet and project management journals, gathering procedures, books. As the result of this stage, 30 factors affecting cost overrun for bridge construction were identified. These factors were categories in nine groups as: Finance related, Contract related, Planning related, Design related, Material, Labour and equipment related, Owner related, Contractor related, Consultant related and Miscellaneous.
B. Questionnaire Design
Likert interval Scale is used for preparing the questionnaire survey is being implemented to determine the view of, clients, consultant, designers and contractors relating the cost overrun factors. This questionnaire is being delivered to contracting, project management consultant and client representatives, who has associated or currently associated with flyover bridge projects.
IV. DATA ANALYSIS
Data analysis is the highly complex work and manipulation analysis with simple instruction SPSS software is uses by market researchers, survey companies, marketing, research education and other
A. Top 10 Cost Overrun Factors
Table 1 Top 10 Cost Overrun Factors
Sr. No. |
Category |
1. |
Type of project and Complexity of project |
2. |
High interest rates and penalty charged by banks |
3. |
Client’s interference during construction project decisions and quick construction instead of quality |
4. |
Technology advancement affect |
5. |
Buying material on credit affect the project cost. |
6. |
Survey of the locationaffect the cost |
7. |
Political communication among different agencies |
8. |
Site sources and location can affect in overrun cost |
9. |
Implementing an effective safety, quality assurance program and Communication system among project is important |
10. |
Fraudulent practices and kickbacks can affect in cost |
Table 2 Descriptive Statistics
|
Mean |
Std. Deviation |
N |
Experience of respondents |
2.0889 |
1.06221 |
45 |
Type of project and Complexity of project affects to the cost. Is it important factor in finance? |
1.5556 |
.72474 |
45 |
High interest rates and penalty charged by banks affects to cost overrun. |
1.7333 |
.96295 |
45 |
Cost affects in finance liquidity with contractor of project. Are you agree? |
1.9111 |
.79264 |
45 |
Are you agree that Contractual relationship affects to the cost? |
1.9333 |
.75076 |
45 |
Cost affects in procurement between bidding /tendering time. Are you agree? |
1.8667 |
.72614 |
45 |
during construction project decisions and quick construction instead of quality can affect in cost as a factor. |
1.7111 |
.81526 |
45 |
Are you agree that changes procurement method affects to the cost? |
2.3333 |
1.12815 |
45 |
Technology advancement affect. Is it important factor? |
1.8667 |
1.01354 |
45 |
Size of the organization and involvement of the project progress affect. Are you agree? |
1.9111 |
.84805 |
45 |
Buying material on credit affect the project cost. Are you agree? |
1.6444 |
.80214 |
45 |
Are you agree that planning and processing should not late which can affect in overall cost? |
1.8889 |
.88478 |
45 |
Survey of the location can affect the cost. Are you agree? |
1.8444 |
.95240 |
45 |
Escalation of material and labour price affect in the cost. Is it important factor? |
2.0889 |
.94922 |
45 |
Progress monitoring, planning effort affect to the cost . Are you agree? |
2.0444 |
.82450 |
45 |
shortage of equipment labour and material affects in cost. Are you agree? |
1.8889 |
.83182 |
45 |
High Mobilization & maintance cost of equipment affect in cost. Is it important factor? |
1.8444 |
.82450 |
45 |
Control mechanism of the project on contract affects in overall cost. Are you agree? |
1.9556 |
.95240 |
45 |
Poor site management and supervision can affect in cost. Is this important factor? |
1.8667 |
.96766 |
45 |
Unnecessary techniques used for construction can affects cost. Are you agree? |
1.9111 |
.90006 |
45 |
Site sources and location can affect in overrun cost. Are you agree? |
1.9111 |
1.01852 |
45 |
consultant in late reviewing and approving running bill (RA) can affect in overrun cost. Is it important as a factor? |
1.8222 |
.88649 |
45 |
Different consultant for design, supervision and contract affects in cost. Are you agree? |
1.8000 |
.84208 |
45 |
Implementing an effective safety, quality assurance program and Communication system among project is important . Are you Agree? |
1.9556 |
.97597 |
45 |
Unexpected geological /season conditions affect in cost. Is it important as a factor to notice at earlier stage? |
1.8889 |
.91010 |
45 |
Political communication among different agencies can affect in cost. Is it important factor? |
1.9556 |
1.06506 |
45 |
Fraudulent practices and kickbacks can affect in cost. Are you agree in this factor? |
1.9111 |
.90006 |
45 |
local traffic issues affect to the cost overrun while constructing flyover Bridge . Are you agree? |
1.9778 |
.96505 |
45 |
land acquisition for construction affects in cost overrun. Are you agree with this factor? |
1.7778 |
.76541 |
45 |
Idle labour, machinery and daily supply of the material affect Cost overrun. Are you agree with this factor? |
2.2889 |
1.01404 |
45 |
Strike, regulation, accident, global pandemic affects in cost overrun. Are you agree with this factor? |
1.8222 |
.96032 |
45 |
V. ACKNOWLEDGEMENT
Foremost, I would like to express my sincere gratitude to my advisor Assistant Professor Nimita Gujar for enlightening me at the first glance of research, and for his patience, motivation, enthusiasm, and immense knowledge. His guidance helped me in all the time of research and writing of this thesis. I could not have imagined having a better advisor and mentor for my project work. I am extremely thankful to Dr. Bhavesh Mewada, Principal, PIET for providing me infrastructural facilities to work in, without which this work would not have been possible. I would also like to thank our concrete lab assistant Harshad Kapadi and Anup Kude for their support whenever I needed. At the last but not least I would like to thanks my all the teacher and friends to helping me.
A structured questionnaire survey approach was used to study the impact of various attributes and factors affecting construction projects performance for the factors analysis in flyover bridge construction industry. thirty (30) factors were considered in this study and were listed under groups based on relevant literature review and data collected. 58 questionnaires were distributed as follows: (58 Forms were distributed among different engineer who were releated to flyover bridge construction were received as respondents. Among them 44 forms were respondent. The results were analyzed, discussed to identify the most important factors, in which Likert 5-point Scale was used for preparing the feedback form spss tool was used for the analysis to determine clients, consultants and contractors perception of construction projects of flyover bridge According to the questionnaire was prepared send to clients, consultants and contractors, engineers and data was collected to analysis the factors for flyover bridge construction
[1] WN Kawmudi and SD Jayasooriya (2021) IDENTIFICATION OF SIGNIFICANT FACTORS INFLUENCING COST OVERRUNS IN CONSTRUCTION PROJECTS OF SRI LANKA [2] Chhavi Gupta and Chitranjan Kumar (2020) Study of Factors Causing Cost and Time Overrun in Construction Projects [3] A.Cindrela Devi1,and K.Ananthanarayanan (2017) Factors influencing cost over-run in Indian construction projects [4] Agarwal, M. (2013). International Journal of Advanced Research in Computer Science and Software Engineering, 3(10), 572–576. [5] Jalaei, F., & Jrade, A. (2014). Construction Research Congress 2014 ©ASCE 2014 140. Construction Research Congress 2014, (2008), 140–149. https://doi.org/10.1061/9780784413517.176 [6] Knight, K., & Robinson Fayek, A. (2002). Use of Fuzzy Logic for Predicting Design Cost Overruns on Building Projects. Journal of Construction Engineering and Management, 128(6),503–51 https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(503) [7] Ling, F. Y. Y., Ke, Y., Kumaraswamy, M. M., Asce, M., & Wang, S. (2013). Key Relational Contracting Practices Affecting Performance of Public Construction Projects in China. Journal of Construction Engineering and Management, 142(March), 1–12. https://doi.org/10.1061/(ASCE)CO.1943- 7862 [8] Literature, B. (1999). EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES, 2(September), 15–17 [9] Megha, D., & Rajiv, B. (2250). A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context. International [10] Journal of Emerging Technology and Advanced Engineering Website: Www.ijetae.com ISO Certified Journal, 9001(3), 396–404. [11] Ramabodu, M. S., & Verster, J. J. P. (2010). Factors Contributing to Cost Overruns of Construction Projects. Proceeding of ASOCSA 5th Built Environment Conference, Durban South Africa, 131–143. Retrieved from https://www.irbnet.de/daten/iconda/CIB_DC22746.pdf [12] Rathi, A. S., & Khandve, P. V. (2016). Study of Factors Influencing Cost Overruns?: An Overview. International Journal of Science and Research (IJSR), 5(3), 334–336. [13] Shanmugapriya, S., & Subramanian, K. (2013). Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects. International Journal of Emerging Technology and Advanced Engineering, 3(10), 734–740. [14] Tejale, D. S., Khandekar, S. D., & Patil, J. R. (2015). Analysis of ConstructionProject Cost Overrun by Statistical Method. International Journal of Advance Research in Computer Science and Management Studies, 3(5), 349–355. [15] The demand for more construction of all types , coupled with an ailing national economy and a tight monetary supply , provided the construction industry with a bigger challenge to cut costs . The problems of the high costs of contracts in all aspects of c. (1988), 114(2), 233–244. [16] Zeynalian, M., Trigunarsyah, B., & Ronagh, H. R. (2013). Modification of Advanced Programmatic Risk Analysis and Management Model for the Whole Project Life Cycle ’ s Risks. Journal of Construction Engineering and Management, 138(January), 51–60. https://doi.org/10.1061/(ASCE)CO
Copyright © 2022 Patel Kiran Kumar, Nimita Gujar. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Paper Id : IJRASET45750
Publish Date : 2022-07-18
ISSN : 2321-9653
Publisher Name : IJRASET
DOI Link : Click Here