• Home
  • Submit Paper
  • Check Paper Status
  • Download Certificate/Paper
  • FAQs
  • Contact Us
Email: ijraset@gmail.com
IJRASET Logo
Journal Statistics & Approval Details
Recent Published Paper
Our Author's Feedback
 •  ISRA Impact Factor 7.894       •  SJIF Impact Factor: 7.538       •  Hard Copy of Certificates to All Authors       •  DOI by Crossref for all Published Papers       •  Soft Copy of Certificates- Within 04 Hours       •  Authors helpline No: +91-8813907089(Whatsapp)       •  No Publication Fee for Paper Submission       •  Hard Copy of Certificates to all Authors       •  UGC Approved Journal: IJRASET- Click here to Check     
  • About Us
    • About Us
    • Aim & Scope
  • Editorial Board
  • Impact Factor
  • Call For Papers
    • Submit Paper Online
    • Current Issue
    • Special Issue
  • For Authors
    • Instructions for Authors
    • Submit Paper
    • Download Certificates
    • Check Paper Status
    • Paper Format
    • Copyright Form
    • Membership
    • Peer Review
  • Past Issue
    • Monthly Issue
    • Special Issue
  • Pay Fee
    • Indian Authors
    • International Authors
  • Topics
ISSN: 2321-9653
Estd : 2013
IJRASET - Logo
  • Home
  • About Us
    • About Us
    • Aim & Scope
  • Editorial Board
  • Impact Factor
  • Call For Papers
    • Submit Paper Online
    • Current Issue
    • Special Issue
  • For Authors
    • Instructions for Authors
    • Submit Paper
    • Download Certificates
    • Check Paper Status
    • Paper Format
    • Copyright Form
    • Membership
    • Peer Review
  • Past Issue
    • Monthly Issue
    • Special Issue
  • Pay Fee
    • Indian Authors
    • International Authors
  • Topics

Ijraset Journal For Research in Applied Science and Engineering Technology

  • Home / Ijraset
  • On This Page
  • Abstract
  • Introduction
  • Conclusion
  • References
  • Copyright

Project Management Using Primavera P6

Authors: Pravin Namdev Pharne, Nagesh Rajshekhar Wagdare, Nilesh Pratap Limbone, Jivan Dinkar Gaikwad

DOI Link: https://doi.org/10.22214/ijraset.2022.42891

Certificate: View Certificate

Abstract

The construction industry is an Integral and developing part of nation\'s infrastructure and industrial growth. In that Construction sector construction manager\'s has to deal with lots of problems regarding time management and its limitations. Safety issues, change in nature work, budget constraints etc. According to previous observation and experience proper skillful management it is very essential to resolve and reduce these issues effectively. Primavera P6 software can overcome these issues adequately and efficiently. Effective time planning is very important in determining success of any project, poor planning and controlling of project will causes delay. In this project, primavera P6 software help the planning scheduling, resource allocation and time help the resource allocation and time management.

Introduction

I.  INTRODUCTION

Large construction project with huge budget it becomes very difficult for project team to handle the task so it becomes very necessary to provide tool in hand of project team that keep a track a activities. Primavera P6 software from product from Oracle is very powerful tool to present the efficient management in hands of project team. It helps in planning controlling and scheduling effectively. The quality of schedule generated from the software often lacks detail and the purpose of the software in adding value to the project is generally not met by the users in India. In addition to provide insight on various project tasks, their inter relationship, dependencies to predict total project duration during planning phase the schedule should be comprehensive enough to let the user understand in detail the purpose of various activities in the schedule. In today’s world construction industry is one of the most widely used and rapidly booming industry of our nation and across the world. In this project we have studied a road project of 1 Km length by conventional method of planning and using primavera P6 software planning. Comparative study of both conventional and primary software is given and the primavera gives better results.

II. LITERATURE REVIEW

  1. Satinder Chopra: concluded that the Activity ID and Activity Description both the most unused part can greatly enhance the quality of the schedule if used properly. It is the duty of the planning team to carefully decide the Activity ID structure in advance so, that schedule preparation flows smoothly without any conflicts. Further research on how other fields like Original duration, Remaining Duration, Tasks bars in the Gantt chart, Start and Finish dates can be presented to give maximum understanding to the user for efficient schedule development
  2. V. Dhanalakshmi (2016): Study deals with the project monitoring process of the economical method of transporting a pipeline construction was completed in Ennore-Trichy-Madurai. Construction work and actual progress is a comparison between the planned progress of performed in this study using project management software Primavera P6.
  3. P. Esaki Thaana: Found time management system is considered to perform a key role in organization, which is responsible to complete the project in a specific time, budget cost within a certain period of time. Poor time and cost performance are major problems faced by construction industry. The main objective of this research is to prepare the proper planning and scheduling for the 6 lanes road work construction at VOC PORT TRUST, Tuticorin. Time management and time control are done by primavera P6 software. The main advantage of project was timely execution and completion of the project using primavera P6 software. The road construction project has completed prior to the contract duration.
  4. Y. Umesh (2015): Proper planning and scheduling is very essential in projects for sinking and scheming delays of the project. Extensive amounts of time, money, resources are wasted each year in a construction industry due to improper planning and scheduling. With globalization the construction projects have become infinite and complex. Planning of such projects requires huge amount of documentation work, which can be reduced with the help of project planning software. These study are to plan, schedule, and track a residential project with help of primavera software, study the results generated, it is possible to propose which method is suitable for the chosen residential project.
  5. B.S.K.Reddy (2015): They did resource optimization exercises on two on-going projects in Dubai, UAE. They individually leveled and then combined option   with aggregated and then leveled clearly indicates reduction in demand of resources by 5.65% in later option, which could be best considered for economy. They concluded Resource leveling at project job site and forwarding demand leads a possible sharing of resources among projects.
  6. E. Suresh Kumar (2015), Scheduling using Primavera Software is a development which involves estimation, sequencing the activities, resources allocation and timing. The construction scheduling is to complete the project in time and equal the resources with the allocated time. Scheduling using primavera Software gives good controlling.
  7. Ismail Abdul Rahman: study identified time management together with their effectiveness level in large construction projects. From the construction organization that deals with huge projects data was collected. Relative Importance Index calculation was employed to assess the level of effectiveness which is helpful for time management techniques and software adopted in the construction project.

III. STEPS INVOLVED IN SCHEDULING

A. Make Schedule

To make a schedule for any project, first of all collect data available for the project. Subsequently the following steps can be followed in Primavera.

B. Creating EPS

To create an ideal schedule for any project, first step is to collect data available for the project. The following steps can be followed in Primavera P6 software.

Create the complete structure of the company with its branches, which is executing the project using primavera P6. This is known as Enterprise project structure (EPS).show in fig

C. Organizational Breakdown Structure (OBS)

After the EPS, OBS is made which is a hierarchical shape structure that shows the persons responsible for projects.

IV. METHODOLOGY

D. Work Breakdown Structure (WBS)

WBS elements have defined and organize the project elements. WBS is a hierarchy of a project work that must be accomplished to complete a construction project WBS hierarchy structure with top level WBS   element being equal to that of each EPS node of the project.  Each WBS element contains more detailed in WBS levels,Activities or both resource constrains.

E. Creating a Calendar

The calendar can create and assign it to each

These calendars define the available work hours in each calendar days. Also specify national holidays, workdays and resource. Fig no 4 shows calendar

F. Relationship Between Activity

By assigning succeeding, preceding activities with significant relationship to the overall project activities  form a network, scheduling the activities should be connected to each other.

  1. Finish to start (FS)
  2. relationship Start to start (SS)
  3. relationship Finish to finish (FF)
  4. relationship Start to finish (SF) relationship

G. Advantages

  1. It helps easily prepare and control project things to do.
  2. It optimizes management off resources.
  3. It offers clear field of vision of what is taking in the project.
  4. It allows quick and easy forecasting connected with WBS’s things .
  5. You can monitor progress along with view past period efficiency for credit reporting purposes.

H.  Activity Dates

The following types of project activity dates available in the primavera; actual start, planned start, actual finish, planned finish.

I.  Creating Baseline

A complete copy of the original schedule is a simple baseline plan which provides a target against which a project’s performance is tracked. Choose project. Maintain baseline. Then add and save a copy of current project as a new baseline B1. Then choose project baseline as B1 and assign primary baseline as B1. Daily updates to be made. firstly Start date and end date. Choose the activity to be updated. Then in the activity details window, select status tab. Then tick mark started if the activity has been started and select the date. Tick mark finished if the activity has been finished and select the finish date.

Comparison

Parameters

Conventional        method  

Primavera Software

•Planning and scheduling

In conventional method there is some inefficient planning

Proper planning and scheduling is optimized

•Management

Due to poor planning and errors results in improper management

Due to proper planning and using resources results in execution of work.

•Cost

Cost may vary due to errors

Cost remains constant throughout the work

•Controlling and monitoring

Due to manual planning difficulties in controlling the work

Effective controlling monitoring is achieved

V.  OBSERVATION

We studied a 1km length bitumen road. It was observed that after planning and scheduling using Primavera the cost was reduced by 47,970 and with conventional planning the cost was 6,71,200. By using Primavera software the cost was 6,23,230. Hence cost reduced by 7-8%.

Conclusion

Planning, monitoring and controlling, as well as the need and effectiveness of project management software like Primavera P6 in a construction project of this study was to understand the role of monitoring and control in the progress and timely completion of a construction project. Delays in construction project is minimized by using primavera software. Effective handling of materials and resources is optimized by using Primavera. The study proved to be a guideline in understanding the progress of construction work and also to identify the specific problems arising during the process. Hence the study gives results about cost reduction and effective management of project. Results of this study show the drawbacks of the present project management system in running project. An efficient and cost effective new project management plan is brought to conclusion.

References

[1] Satinder Chopra, Arvind Dewangan, Developing an Efficient Schedule in Primavera P6: Significance of Activity ID & Descriptions, International Journal of Innovative Research in Science, Engineering and Technology(An ISO 3297: 2007 Certified Organization) Vol. 3, Issue 7, July 2014 [2] V.dhanalakshmi, high cost infrastructure report monitoring by p6 software, international conference on engineering innovations and solutions(ICEIS – 2016) [3] P. Esakki Thangam, R. Magdalene Benila, Planning, Scheduling and Time Management of Six Lanes Road Construction Work at V.O.C Port Trust using Primavera P6 Software IJSTE - International Journal of Science Technology & Engineering | Volume 2 | Issue 11 | May 2016 [4] Unmesh. Y. Polekar, Rohit. R. Salgude Planning, Scheduling and Tracking of a residential Project using Primavera Software, International Journal of Advance Research in Computer Science and Management Studies, Volume 3, Issue 5, May 2015 [5] T. Subramani, A. Sarkunam, J. Jayalakshmi, Planning and Scheduling of High Rise Building Using Primavera, T. Subramani et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 6(Version 5), June 2014, pp.134-144 [6] Vishal Annappa Nimbal, Prof. Balasaheb Jamadar, Planning, Scheduling and Allocation of Resources for multi-storied Structure using Oracle’s Primavera p6 software, International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 [7] Ms.Deepika Kand Mrs.Suchithra S, Study on effective scheduling and cost management of a project, International Journal of Modern Trends in Engineering and Research (IJMTER) Volume 03, Issue 03, [March – 2016] [8] P Raghunath Reddy, B.Harish Naik Planning and Resource Scheduling of Residendial (G+7) Project Using Primavera International Journal of Innovative Research in Science,Engineering and Technology(An ISO 3297: 2007 Certified Organization) Vol. 5, Issue 10, October 2016 [9] Vipin Kumar Dr. Shreenivasreddy Shahpur Maneeth P. D. Brijbhushan S., Analysis of Academic Building by Planning, Scheduling & Resource Allocation Using Oracle® Primavera P6, © 2017 IJSRST Volume 3 Issue 6 [10] Mr. akash rajkumar wadhwa,mr. dattatray santram shinde, project management using primavera p68.2 international journal of innovations in engineering research and technology [ijiert] novateur.

Copyright

Copyright © 2022 Pravin Namdev Pharne, Nagesh Rajshekhar Wagdare, Nilesh Pratap Limbone, Jivan Dinkar Gaikwad. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

IJRASET42891

Download Paper

Authors : Nagesh Rajshekhar Wagdare

Paper Id : IJRASET42891

Publish Date : 2022-05-18

ISSN : 2321-9653

Publisher Name : IJRASET

DOI Link : Click Here

About Us

International Journal for Research in Applied Science and Engineering Technology (IJRASET) is an international peer reviewed, online journal published for the enhancement of research in various disciplines of Applied Science & Engineering Technologies.

Quick links
  • Privacy Policy
  • Refund & Cancellation Policy
  • Shipping Policy
  • Terms & Conditions
Quick links
  • Home
  • About us
  • Editorial Board
  • Impact Factor
  • Submit Paper
  • Current Issue
  • Special Issue
  • Pay Fee
  • Topics
Journals for publication of research paper | Research paper publishers | Paper publication sites | Best journal to publish research paper | Research paper publication sites | Journals for paper publication | Best international journal for paper publication | Best journals to publish papers in India | Journal paper publishing sites | International journal to publish research paper | Online paper publishing journal

© 2022, International Journal for Research in Applied Science and Engineering Technology All rights reserved. | Designed by EVG Software Solutions